We know from our many conversations with owners corporation (OC) committee members that OC projects:
Don’t always move forward in a linear way. Sometimes a project idea will reveal the need for a side project to be completed before the initial idea can progress. For example, installing solar on an apartment building sometimes triggers a switchboard upgrade
Takes time: weeks, months or even years
We’ve used this knowledge to help design the project.
Flexibility
It was important we offer participating committees flexibility in how we supported their electrification ambitions, so we developed an MOU for committees to review and edit. The MOU focuses on how we and the committee work together, rather than being rigid about what we work on (as long as it relates to the transition to building electrification). The MOU also has a strong focus on protecting privacy of participants.
If you’re curious, you can read the draft MOU.
Allowing time
Despite this project being delivered with time-bound grant funding, we knew it was important to give committees time and space to consider their involvement in the project. Committee members aren’t getting paid. They’re working as volunteers for the benefit of their building and owners corporation. We want to respect their time and capacity limits.
What can slow committees down? The committees we’re currently in discussion with, have a range of other things going on. For example:
A committee member was on holidays and the committee was keen to see the electrification report before starting another partnership project
Another was in the middle of transitioning to a new owners corporation manager
And the third was dealing with urgent leaking and building engineering issues. They needed to focus on that before the idea of participating in our Action Research project could be officially brought to the committee for a decision. There’s only so much a volunteer committee can do at any one time!
We have tried to offset a slow start by piggybacking on an existing City of Melbourne project, which will essentially fast-track the energy assessment process (more on this in our first blog post).
We started recruitment in late September. As of today, we have three owners corporations keen to participate but no signed paperwork as yet.